A workshop can generate many improvement ideas in a short time.
This is visible, motivating and often impressive.
Nevertheless, the economic benefit of a Value Analysis project only materialises later:
When selected solutions are actually implemented.**
Implementation should therefore already be prepared during the project.
The difference between an idea and an action
An idea might be, for example:
“Simplify the component.”
An action that can be implemented needs considerably more information:
- What exactly is to be changed?
- Which function must still be performed?
- Which requirements are affected?
- Who will take on the technical elaboration?
- What savings are expected?
- What effort is involved?
- What investment is required?
- What risks are there?
- By when must a decision be made?
Only then does an idea become a manageable work package.
Consolidating concepts before implementation
Many ideas cannot be implemented individually.
They influence one another and have to be combined into technical concepts.
Before implementation, the following should therefore be clarified:
- Which ideas together form a viable concept?
- Which variants should be pursued further?
- What dependencies exist?
- What effects are there on cost, quality and customer value?
- Which technical tests are still required?
Business Case and economic impact
For larger actions, a theoretical saving is not enough.
Relevant factors include, for example:
- change in manufacturing costs
- one-off development costs
- investments
- tooling costs
- change costs
- expected volumes
- timing of the impact
- possible follow-on costs
- risks
This makes it possible to assess whether an action makes economic sense.
Define responsibilities clearly
A common reason for stalled implementation is a lack of ownership.
Each prioritised action should therefore have at least:
- an owner,
- a concrete next step,
- a target date,
- a documented assumption about its impact
- and a clear need for a decision.
This creates transparency.
Regular implementation reviews
After the actual workshop, the general conditions often change.
Technical tests provide new insights, supplier quotations change cost estimates and requirements become more precise.
Regular reviews therefore make sense.
They can be used to check:
- What is the current status?
- Is the originally assumed potential still achievable?
- What obstacles are there?
- What decision is needed?
- Does the concept need to be adapted?
- What new actions have emerged?
Why the original project team remains important
Many implementation issues are cross-functional.
A design change can affect:
- procurement,
- production,
- quality,
- logistics,
- approval,
- Service
- or customer requirements
at the same time.
It is therefore often advisable to keep at least a core of the original project team involved during implementation.
Implementation at Value Coaching
Value Coaching’s current description of its consulting approach explicitly treats implementation as part of the process.
Selected actions are converted into specific implementation packages and followed up in implementation reviews.
This means the Value Analysis project does not end with the choice of concept but keeps the economic impact in view.
Further reading
- The Value Analysis Work Plan in 10 steps
- Evaluation in Value Analysis: prioritising ideas transparently
- Cost reduction project and cost reduction workshop
- Project Potential Assessment: selecting the right projects
- Our consulting process for Value Analysis projects
- Value Analysis project examples and references
- Business Case for cost reduction measures